2.34 Driving Whole-of-life Efficiencies through BIM and Procurement

Infrastructure
2.34
Complete
Core

2014 - 2015

In 2013, the Australian Department of Industry identified lifting productivity and economic growth as one of the most important challenges that Australia is facing.

Overview


In 2013, the Australian Department of Industry identified lifting productivity and economic growth as one of the most important challenges that Australia is facing. In 2014, the Australian Productivity Commission highlighted that a more widespread adoption of Building Information Modelling (BIM) could enhance productivity across the industry and in turn have a positive impact on the cost structure of infrastructure projects.

Findings from SBEnrc Project 2.24 Integrated Project Environments (2013-14) pointed to the need for: (i) more effective procurement models that allow the use of BIM as a tool for whole-of-life asset management; and (ii) the integration of measurable indicators that can be used from the early procurement phases and carried through the entire life-cycle of constructed assets.

This project (2014-15) aimed to identify and assess this added value of creating industry benchmarks for implementing BIM in whole-of-life asset management, with a focus on procurement methods and efficiency gains for infrastructure and building. Outputs from this project will provide a base for clients to improve their approach to implementing BIM and monitoring their progress towards fully integrated whole-of-life asset management systems.

Project Objectives

  • Define indicators to measure tangible and intangible benefits of BIM across a project’s life-cycle in infrastructure and buildings.
  • Pilot test a whole-of-life BIM value realisation framework on leading infrastructure and building case studies and validate the NATSPEC National BIM Guide within this context.

Industry Outcomes

This project delivered:

  • BIM Value Realisation Framework and BIM Value, an interactive online tool to develop a benefit realisation and monitoring strategy, in line with NATSPEC National BIM Guide.
  • Three Australian exemplar case studies across design, construction and asset management showcasing benefits, tools and metrics for uptake of BIM.
  • Advanced knowledge base of benefits from transitioning from 2D asset management and delivery systems to 3D integrated digital built environments.

Although there are numerous studies and articles on the benefits of BIM, it can be difficult for organisations to assess its potential value for their particular purposes. Even when they have decided to use BIM, it is often not clear how to best implement it.

The BIM Value tool has been developed by the Sustainable Built Environment National Research Centre (SBEnrc) in partnership with NATSPEC to address these issues. It is based on a comprehensive methodology developed as part of SBEnrc’s research based on academic and industry research. The content was developed in close consultation with industry, government and research organisations across Australia and internationally. This ensures that it is relevant to a range of stakeholders. The information used to develop the tool is detailed in the book Delivering Value with BIM – A Whole-of-life Approach by Adriana Sanchez, Keith Hampson and Simon Vaux to be published by Routledge in March 2016. Work to improve the tool will continue over 2015 – 2017.

BIM Value is a free open-access tool that provides managers with a step-by-step guide to identifying potential benefits, metrics and tools for implementing BIM.

Case Studies

This project leveraged off national exemplar projects through case studies to develop and test the value realisation framework:

Design – New Generation Rollingstock Maintenance Centre, Queensland
This purpose-built train maintenance depot is being delivered at Wulkuraka in Ipswich as part of a AUD$4.4b public-private-partnership. It is part of the Queensland Government’s New Generation Rollingstock project which will ultimately provide 75 new six-car trains, maintenance of these trains for a period of around 30 years, and construction and maintenance of a train maintenance depot. The Queensland Department of Transport and Main Roads awarded the contract to a consortium comprising Bombardier Transportation, John Laing, ITOCHU Corporation and Uberior Infrastructure Investments. Laing O’Rourke is the Design and Construct contractor for the train maintenance depot.

For more information about the New Generation Rollingstock project please go to: https://www.tmr.qld.gov.au/ngr

Construction – Perth Children’s Hospital, Western Australia
This AUD1.2 billion project will replace Princess Margaret Hospital as Western Australia’s dedicated children’s hospital to provide the best possible clinical care for future generations and as a location for outstanding paediatric research. The hospital project team has endeavored to carry out extensive consultation and research to benchmark their work against national and international best practice design and service models. The project is currently being carried out under a Stage One Managing Contract awarded to John Holland Pty Ltd. This project is under construction and due for practical completion in July 2015.

For more information about the Perth Children’s Hospital please go to: Perth Children’s Hospital

Asset Management – Sydney Opera House, New South Wales

The Sydney Opera House is a global icon and probably one of 20th century’s greatest buildings receiving over eight million visitors every year. The House is currently the subject of major construction work including a new set of tunnels for servicing and car parking and a sub-level loading dock. In 2007, the CRC for Construction Innovation, the predecessor to SBEnrc, published Adopting BIM for Facility Management: Solutions for Managing the Sydney Opera House which investigated the opportunity for implementation of BIM to support enhanced asset management. This project started the journey of the Sydney Opera House towards more advanced use of BIM for asset management which is still ongoing. This case study will revisit this exemplar project and review the value of BIM in practice.

For more information about the Sydney Opera House please go to: Sydney Opera House

Expert discussion session on the topic of information integration with four academic and industry experts Kalle Kähkönen from Finland, Chrisna Du Plessis from South Africa and Shyam Sunder the US at the CIB World Building Congress 2016 in Tampere, Finland (01 June 2016)

Delivering Value with BIM (outcome of Project 2.34) launched and endorsed by an adviser to the US Government Dr Shyam Sunder at CIB World Building Congress, Tampere, Finland (01 June 2016)

CIB Task Group 90: Information Integration in Construction (IICON)

2.CIB-logo-onwhite-withsloganCMYK

SBEnrc is leveraging on the international collaboration network formed in the SBEnrc Project 2.7 Leveraging R&D Investment for the Australian Built Environment through the International Council for Research and Innovation in Building and Construction (CIB) Task Group 85 R&D Investment and Impact, to form a new Task Group 90 focused on Information Integration in Construction (IICON). This group will compliment activities of SBEnrc Project 2.34 Driving Whole-of-life Efficiencies through BIM and Procurement and continue the research efforts started in Project 2.24 Integrated Project Environments to add more value to our Centre Partners.

IICON activities will focus on creating a more effective and reflective industry and deliver benefits to public and private asset owners through:

  • efficient knowledge creation, preservation and integration across the life-cycle of constructed facilities
  • relevant, reliable, interoperable and long-lasting data and information gathering and analysis
  • monitoring and feedback from end-users into the different stages of design, construction and asset management of buildings and infrastructure.

Research Team

Catherin Bull AM FAILA MAICD

Chair, Project Steering Group

Catherin Bull AM FAILA MAICD

Emeritus Professor
Principal Consultant at Catherin Bull Urban Design and Strategy, Landscape Architecture

Professor Keith Hampson

Project Leader

Professor Keith Hampson

BEng (Hons), MBA, PhD, HonFIEAust, FTSE, FAICD

k.hampson@sbenrc.com.au

Adriana Sanchez

Research Associate

Adriana Sanchez

BChem MSc (SRM)
Curtin University

a.sanchez@sbenrc.com.au

Professor Sherif Mohamed

Research Leader – Housing and Buildings Sector

Professor Sherif Mohamed

MEng PhD PMP
Griffith University

s.mohamed@griffith.edu.au


Research Partners

Aurecon
BGC Australia
Curtin University
Goverment of Western Australia
Griffith University
John Holland
Transport for NSW
Queensland Goverment
Queensland University of Technology
Swinburne University of Technology


Additional Resources

Let’s Talk